The Capital Construction Department of the Kherson City Council has ordered the construction of six emergency reserve gas boiler houses. According to journalists, the total cost of the orders is about UAH 444 million. The equipment is intended to strengthen the resilience of heat supply in the front-line city.<\/strong><\/p>\n
This was reported on November 16 by "Nashi Groshi" with reference to data from the electronic public procurement system Prozorro.<\/p>\n
The contracts relate to the reconstruction of heat supply facilities with the installation of emergency reserve gas block-modular boiler houses. The customer is the Capital Construction Department of the Kherson City Council.<\/p>\n
The work includes not only the purchase of equipment, but also the preparation of project documentation, its examination, and direct construction. This approach allows ordering a full range of works within one contract.<\/p>\n
In the open procurement data of the Kherson City Council, among the contractors for similar projects are the consortium "Teplomodul Group" and the private enterprise "Akvalait".<\/p>\n
In particular, in November, the consortium "Teplomodul Group" received four contracts for the construction of reserve boiler houses with a total value of about UAH 281.9 million, according to documents from one of the procurements and other published contracts.<\/p>\n
Earlier, in October, "Nashi Groshi" reported on another package of contracts for reserve boiler houses with a total value of UAH 476.26 million. Since some of the procurements may have been carried out repeatedly, these amounts cannot be automatically summed without comparing the contracts.<\/p>\n
For Kherson, the creation of reserve heat sources is of particular importance due to constant Russian attacks on the city's infrastructure. Block-modular boiler houses should provide alternative heat supply to the housing stock and urban infrastructure facilities in case of problems with the main system.<\/p>\n
The development of reserve heat supply is provided for in plans to increase the energy resilience of the region. At the same time, the conclusion of contracts by itself does not mean the completion of construction or the commissioning of new capacities.<\/p>\n
Based on materials: "Nashi Groshi"<\/a>, Prozorro<\/a><\/p>