The parliamentary Temporary Investigative Commission revealed a significant discrepancy between budget advances and documentary evidence of construction of protective structures for energy facilities in Kyiv region. Out of almost UAH 824 million in prepayment to contractors, only UAH 23 million has been settled by acts of completed work.

This was reported by the head of the parliamentary TIC, People's Deputy Lesia Zaburanna, who published the results of financial and engineering-technical analysis of 26 contracts of the Department of Regional Development of Kyiv Regional State Administration.

According to the inspection results, the total estimated cost of construction of protective structures after adjustment increased from UAH 1.84 billion to UAH 2.28 billion. At the same time, none of the 26 facilities as of November is completed and commissioned.

Contractors have already been transferred UAH 823.99 million in advances, of which only UAH 23.02 million, or 2.79%, has been settled with documents. Another UAH 87.45 million was paid separately based on acts of completed work.

Thus, about UAH 801 million of prepayment remains not settled by relevant acts. At the same time, Zaburanna emphasized that this amount is not established losses. It is necessary to check the actual volumes of construction, use of funds, and availability of purchased materials.

According to the deputy, a significant part of contracts is concentrated in three companies. In particular, LLC "Consulting-Bud" received 14 contracts with a total value of UAH 926.85 million and UAH 439.85 million in advances. The company LLC "UBK "Y.B.C." was transferred UAH 324.8 million in prepayment under nine contracts.

Certain questions arose in the TIC regarding the combination of design and construction functions. The commission considers it necessary to check a possible conflict of interest and adequacy of technical control.

In addition to the financial component, experts drew attention to the difference between formal construction readiness and the actual ability of structures to protect energy equipment. According to the client's reporting, the average readiness of facilities is 53-55%, but partially completed works do not yet mean the creation of full protection.

Based on the analysis, Zaburanna proposed to conduct a priority financial and engineering audit within 14 days. It is proposed to involve the State Audit Service and relevant technical experts in the inspection.

Among the proposals are also a transition to payment for actually confirmed works, checking the grounds for return of unearned advances, and accelerating the transfer of unfinished facilities to the Restoration Agency without stopping construction.

The deputy emphasized that the inspection of possible financial violations should take place in parallel with the completion of protective structures, as delays create additional risks for energy infrastructure.

Earlier, "Kurs Ukrainy" reported that following the meeting on November 12, the parliamentary TIC decided to initiate inspections of possible violations during the construction of energy protection structures in Kyiv region. New data specify the financial status of projects based on the analysis of contracts and payments.

Based on materials: Lesia Zaburanna