None of the six reserve boiler houses being built to provide heat supply in the Darnytska TPP area has been put into operation in Kyiv yet. Some facilities are at the final stage of construction, but there are no concrete terms for their launch.
The head of the State Agency for Restoration and Infrastructure Development, Ivan Fedorov, said this in an interview with "Ekonomichna Pravda" published on November 23.
According to him, the Agency is working on the creation of six reserve heat supply facilities for buildings that depend on the Darnytska TPP. However, during the previous stages of the project, a number of important details were not taken into account, so the work has to be accelerated.
"A lot of work was started, a lot of details were missed. Now we are catching up, doing, we will do it," Fedorov noted.
When journalists directly asked about the readiness of reserve capacities, the official confirmed that no boiler house is operational yet. According to him, it was impossible to put the facilities into operation earlier.
Fedorov explained that construction depends on several factors at once: readiness of equipment, completion of construction and engineering works, as well as connection of the necessary networks. At the same time, different contractors are progressing at uneven speeds.
By the end of 2026, the Restoration Agency plans to provide 80% of buildings in the Darnytska TPP service area with a reserve heat source. This refers specifically to buildings that depend on this combined heat and power plant, not the entire housing stock of the capital.
At the same time, Fedorov did not specify how many reserve boiler houses will start operating first and when exactly heat supply from the new facilities will begin.
Recall that the Darnytska TPP suffered critical damage as a result of a Russian strike on February 3, 2026. The station provided heat supply to more than 1,100 multi-storey buildings in the Darnytskyi and Dniprovskyi districts of Kyiv.
Earlier, on November 12, the Restoration Agency reported the acceleration of construction of two reserve boiler houses. To complete the work, the contractors had to switch to a round-the-clock schedule.
Thus, as of November 23, the reserve heat supply system in the Darnytska TPP area has not yet been put into operation. Its readiness is of particular importance for residents of the left-bank part of Kyiv against the backdrop of the risk of new attacks on energy infrastructure.